|
Building Community
Resilience to Flood Risks in Kaisarganj Block, U.P., India
Bahraich
District in the state of Uttar Pradesh
situated near the southern border of Nepal is a heavy flood prone
zone. Bahraich district gets flooded when there is heavy rain
upstream in the rivers in Nepal and when there is over flow discharge
from the barrages on the Indo-Nepal boarder. Bahraich District
and Kaisarganj Block were submerged from end of July to September
2007 due to four consecutive flooding of the Ghaghara River in
three months.
As per
government reports about 16,000 people were affected by these
floods, out of which 2,000 people were displaced in Bahraich district.
The total affected area was 3,930 hectare, out of which 3,530
hectare, approximately 90% land was agricultural land. The floods
also resulted in 36 deaths in Bahraich district. In Uttar Pradesh,
although maximum devastation was seen in early August, when 2,634
villages were affected , in the beginning of October, 886 villages
were still submerged having seen several cycles of inundation.
The
Initial Assessments:
The first assessment
was undertaken in early August 2007 during the floods with the
objective to assess immediate needs which could be addressed by
direct relief by Malteser International. The second assessment
was undertaken at the end of October 2007 to monitor the ongoing
relief by Malteser International as well as to assess the rehabilitation
needs to further plan a rehabilitation phase.
These
assessments were undertaken by senior staff of Unnati and SSK.
The visits for the assessment were undertaken in cooperation with
the Lucknow based local NGO, Sahbhagi Shikshan Kendra (SSK). Village
level discussions were held with men and women separately on coping
mechanisms, housing needs and options, as well as rescue methods.
Two meetings were conducted with 8 local NGOs who were partnering
with SSK in Bahraich district. Discussions were also held with
Block officials and Disaster Management Department. Consultations
were also held to share experiences and work together with other
international NGOs working in the region.
During the visit to the affected areas, it was
observed that the houses were severely damaged or destroyed as
they were submerged during the long-lasting flood. Most of the
affected families live in the area 4-5 km between the river and
the embankments (bund) built in the 1960s. During the months of
the flooding people survived in makeshift shelters on top of these
embankments. Support from the government was minimal and did not
reach the neediest for reconstruction of their shelters.
People suffered heavy losses of crops and livestock. Loss of work
opportunities in agriculture resulted in severe food shortage
and shortage of cash for survival as most of the families living
in the area are from the marginalized and/ or dalit communities
who depend on daily wages for their survival.
During
the flood, many hand pumps from which people normally would fetch
water were submerged and the other water sources got soiled. In
places of refuge people often had no access to clean water and
suffered from water born diseases.
Emergency response was very slow and minimal. There was a shortage
of rescue devices, especially means of transport, i.e. boats for
people to move within the flooded area to fetch supplies or go
to find work.
The
main stakeholders in the region were the affected community, particularly
dalits and artisan castes like Yadavs, Keots, Godiya, Pasi, Nishad,
Lohars Muslims, Chamars, etc. Most of these community members
are either marginal farmers or agriculture labourers. Some of
them are also involved in share cropping. Due to extensivedamage
of the agricultural lands and
crops, the vulnerability of these community members increased.
Due to loss of work, the coping capacities were low and likelihood
of migration or distress sale of whatever little assets they may
have was very high. Through this project, it was flood Map of
the Region flood Map of Baharaich satellite Image of the Area
Locating the Project Villages and Surroundings envisaged that
the affected community members, particularly the above mentioned
socio-economically marginalised castes, would get some income
through work opportunities and long term habitat security was
to be built into the project.
The
Gram panchayats were the next important stakeholders. They lacked
the capacity to effectively deal with the situation. It was essential
to strengthen them as they are the ones to take decisions in any
emergency situations. The Gram panchayats in Bahraich district
are spread over many hamlets. Thus, the hamlet level units were
considered for developing a preparedness system for the Gram panchayats.
Although
the Block and District level administration were responsible for
managing the disaster response and coordination at the local level,
the government response was limited to early relief work and the
rehabilitation responses were not adequate. Under the Disaster
Management Act, disaster response, preparedness and management
was to be strengthened at the district level but this process
remained out of public scrutiny and not known to people. The government
plans were limited due to lack of people’s participation
and effective implementation models. It was therefore essential
that the knowledge and experiences be shared for further strengthening
of the processes influencing ‘disaster preparedness plans’.
Similar models could be implemented using the opportunities provided
under the various government schemes to ensure Disaster Risk Reduction
(DRR).
Based on the above observations
and discussions with different stakeholders, an intervention
strategy was developed. Further visits were made to the project
area along with local partners to consult with the affected families
on the activities proposed in the intervention strategy before
formulating the final proposal.
Project
Villages
The villages selected for the project were all on the east bank
of the river and west side of the bund (satellite images on previous
page). Thus they were prone to heavy flooding during the monsoons
when the river Ghaghara overflew, eventhough some of the villages
were as far away as 5 km from river. Being close to the river
also meant that the land there is very furtile and productive.
Nearest town from these villages is Kaisarganj, block headquarter
in Behraich district. It is approximately 150 km from Lucknow.
The border with Nepal is approximately 90 km from Kaisarganj.
The villages selected for the project are within 5 to 7 km from
Kaisarganj.
| Baghahiya |
| No. of
Purvas |
BPL Families |
Total
Population |
Male |
Female |
| 02 |
39 |
1210 |
689 |
521 |
| Kandauli |
| No. of Purvas |
BPL Families |
Total Population |
Male |
Female |
| 03 |
349 |
1045 |
569 |
476 |
| Kohali |
| No. of Purvas |
BPL Families |
Total Population |
Male |
Female |
| 01 |
119 |
1239 |
658 |
581 |
| Chulambha |
| No. of Purvas |
BPL Families |
Total Population |
Male |
Female |
| 13 |
148 |
2148 |
1148 |
990 |
| Matarepur |
| No. of Purvas |
BPL Families |
Total Population |
Male |
Female |
| 07 |
483 |
3094 |
1747 |
1347 |
Main Activities:
As discussed earlier, four main activities were defined in the
project.
- Development
of homestead plots
- Raising
of water hand pumps for water source protection
- Cash for
work
- Early warning,
evacuation and rescue trainings
All
these activities were not seen as different components, instead
was developed as an integrated approach for strengthening the
community’s resilience towards flood risks.

Level raising of Homestead
plots and material support
The objective of this activity was not only to create shelter
security but also to build flood resilience by increasing the
height of the homestead plots. Although the community members
had to move to safer places during the few days of flood, the
project sought to ensure that when they came back, they had a
shelter for living. The overall focus was to enable the vulnerable
households on use of wattle and daub technology for construction
of the houses. A technical team would monitor the construction
done by the people and provide them with technological assistance
for constructing better shelter. As labour was required for the
construction of the shelter and hand pump level raising and there
was need for livelihood support, the cash-forwork activity was
targeted the local people.
Analysis of present housing conditions and proposed shelter:
People in this region live in small hut-like houses in settlements
called ‘purva’. A few of these purvas put together
make a village. Most families have a small piece of land on which
they build their houses with locally available wood and grass.
There is generally a little land available for agriculture, where
they produce grains for their yearly consumption and financial
needs.
A
quick assessment of the present housing situation in the region
shows that the quality of housing was very poor. Though there
is ample material available for house construction, due to concurrent
floods and widespread poverty, the housing quality is very bad.
A
typical house in the rural area is built with bamboo or wooden
poles acting as columns. The roof structure is generally made
of bamboo or local wood covered by thatch. Even though bamboo
is available in abundance it is not used for the screen walls,
rather thatch or local grass along with wooden sticks are used
to make wattle and daub construction. Many a times the walls are
plastered with mud, but leaving some parts of the wall exposed.
In some cases the people had also constructed the walls with cob
wall construction. It was also observed that the plinths of the
houses were very low and could not protect the houses from the
floods during the monsoon. The roof did not have enough overhangs
and hence during the monsoons, the mud plaster (in case of wattle
and daub construction) or mud wall (in case of cob construction)
would get washed away every year. Also, the roof made up of thatch
would not withstand the monsoon showers. Overall, the average
life of the house was one or two years only.
To improve this situation, few immediate steps (outlined below)
were considered:
-
It
was important to raise the plinth level of the house such
that it does not get submerged in the floods year after year.
It was observed that a minimum 3 feet level raising was necessary
in almost all cases, while in some the floor level of the
shelter needed to be raised by up to 5 to 6 feet. In order
to protect the raised homestead plot plinth, there was a need
to create a retaining wall. Instead of using brick and cement
which was costly, through various discussions another alternative
was developed. Gunny bags filled with mixture of sand and
cement as retention walling material has been in use locally.
It was identified as most appropriate and cost effective technique.
This technique was adopted in the project by contextual modification
like bamboo reinforcement placed externally. These bags were
covered with mud plaster to further protect against erosion.
In places where the plinth had to be raised more, it needed
to be further protected against soil erosion in monsoon. The
internal area was then filled with soil brought by people
from their agricultural plots. Since the area gets flooded
regularly, it was thought that the next flood would fill up
the excavated part with fertile river soil and therefore the
farming would not suffer.
-
Provide more durable materials so that the life of the house
increases. Thus, Balli (eucalyptus pole) was decided to be
used as column and main structure of the roof. It was also
decided that bamboo could be used for rest of the roof structure.
-
While it was very important to improve the roofing such that
it could resist the monsoon rains it was difficult
to find an alternative to the thatch for roofing material.
Country tiles were not being manufactured anymore in the region
and Mangalore tiles were also not available easily or were
costly. Hence, other options were explored. Development Alternative,
an organisation based in Delhi which manufactures Micro-Concrete
Roofing tiles (MCR Tiles) in their manufacturing unit at Jhansi
was contacted. In the entire shelter programme this was the
only material sourced from outside the region.
-
Materials used for construction of the shelter should be such
that it is affordable to repair the shelter or replace the
parts without requiring high skilled labour, preferably by
the people themselves.
-
As it was observed that the skill for building construction
was very poor in the region, skill up-gradation should be
integrated within the programme. Also the materials used should
be affordable.
Thus, easily available local materials like bamboo, eucalyptus
poles (balli in local language) and mud, which were also affordable,
could be used to construct durable shelter keeping the cost
of construction and subsequent repair within control. Although
all these materials were used by the people to construct their
houses, they were lacking in the skill to optimally utilise
them. Hence they was a need to enhance their skills.
Through community consultation it was decided that balli would
be used as structure of the shelter, while bamboo was also
combined in the roof and walls. It was also decided that the
walls would be made with bamboo mat tied between two columns.
They would then be plastered with mud. Bamboo mat making for
screen wall construction was not common here and would require
new skills, though it is a common way of construction in Assam
and other Himalayan regions, and known as Ikra construction.
It was decided that people would be trained in making bamboo
mat for screen walls.
Selection
of families:
After
selecting the villages, discussions were held with the panchayats
and the people to identify the most vulnerable families. In each
village, a shelter committee was formed to carry out social processes
related to shelter provision. The project team also carried out
an independent vulnerability analysis in these villages to identify
the families requiring shelter support. Based on the inputs from
the village shelter committee, community meetings and consultation
with the panchayat’s the poorest of poor families were identified
to be part of the project.
Special focus was given to single women, disabled, elderly and
refugees who did not have any support. Some families did not have
land, or the land was not sufficient for them to build shelter
and do farming. In some cases, community consultations were held
to provide such families land from the neighbour or community
land . In some cases, the owner of the farm where the family worked
as labourer agreed to give his land for the construction of the
shelter. A community consensus was arrived at so that the shelter
remained with the family even after the completion of the project
when the project team would not be in the village. While selecting
the families, social vulnerability was also kept in mind. All
the 60 families were identified by commuity, based on different
vulnerability criteria.
Process
of Shelter Construction:
Once the families were selected, technical assessment regarding
the shelter needs was carried out by the project engineer with
the selected families. The land was surveyed for area, location,
flood-level history etc. before finalising the exact location,
direction of the shelter and level of the raised plinth.
As
the families selected for the project were poorest of the poor,
some of them did not have enough land to build their house and
some others also faced problems to get the soil for plinth filling.
These issues were solved by discussing with the panchayats or
with help from relativesand neighbours. Most people cleared their
own plots so that the construction could begin. Some families
required the support of cash-for-work programme to do the work.
In case the soil could not be sourced by the owner, the project
team helped source the soil from nearby common plot with help
of the panchayat. In some cases, the programme supported the cost
for trailer to transport the soil. Material for construction was
distributed to the individual families on the basis of estimated
Bill of Quantities (BoQ) on site. Challan was issued for all the
transactions.
The
construction began with marking on the plot along with the family.
First columns were erected with balli (eucalyptus poles) which
were dipped in used engine oil to protect them from white ants
and termites. They were embedded at least 1.5 feet below the ground
to make the construction safe. After the balli columns were erected,
plinth filling was done with help of gunny bags and soil as structure
for roof, with bamboo and balli per the assessed flood level.
Carpentry
work began after the plinth was raised. Badhais (local carpenters)
were appointed as contractors for skilledwork in shelter construction.
Unskilled workers were also appointed through cash-for-work activity
of the project. The main structure of the shelter including roof
structure was constructed before the screen walls were put up.
Initially
it was thought that thatch could be used for the walls and roof
but as thatch was not available during the monsoon the idea of
using thatch was dropped. It was decided to use more durable material
instead. Hence, roofing was decided to be of MCR tiles and the
walls to be made of bamboo mats. The carpenters and the labourers
had to be trained in making the mat for the screen wall. Locals
who were interested in learning new ways of using bamboo were
trained in making the bamboo mat by project engineer. MCR tiles
were the only elements used in the shelter programme that was
not procured from the surrounding. Hence, rest of the money to
purchase the materials as well as labour went into the local economy.
The
first few houses that were constructed using different materials
withstood the floods during the project period. This rebuilt the
faith of the community on raising homestead plots as a measure
for flood resilience to the housing stock. Eventhough people had
to leave due to water surrounding their houses, when they returned,
they had a shelter to live into.
 
Ensuring Safe Drinking
Water by Hand Pump Level Raising

Hand pump level raising was another important activity of the
project. The objective of this activity was to provide safe drinking
water not only during floods but throughout the year.
Hand
pumps were the main source of water for the villagers. People
relied on either government installed, privately owned or community
owned hand pump for their daily domestic water requirements, both
for drinking or
washing purposes.
Due
to the proximity to the river Ghaghara and the flat terrain, it
was observed that the ground water level in the region was very
high. Water was available at 10 to 15 feet depth but this could
not be used for drinking. Potable water was available approximately
at 80 feet depth. Water was abundantly available but the monsoon
posed the problem of water contamination, especially during the
floods. The existing pumps were almost at the ground level, which
were submerged during the floods as the water level used to raise
up to 5 feet or more above the ground level. The villagers did
not have access to potable water during the floods and even after
the water level receded the hand pumps were blocked with silt
and the water was contaminated increasing the risk of an epidemic.
It was necessary to improve the situation of drinking water as
part of flood resilience strategy.
To
involve the local people in the decision making and also for the
people to understand the usefulness of this activity, a Hand Pump
Nigarani Samiti (Hand-Pump caretaking committee) of five to six
members was formed with representatives (especially women representatives)
from different purvas in each project village. These committees
would be pivotal in making decisions regarding the hand pumps
in the village. It would also be active in their maintenance and
other issues related to the hand pump.
On
analysing the situation, the committee felt that there was an
urgent need to raise the levels of the hand pumps which was the
main source of water for the community. The decision was then
taken to raise the levels of the existing pumps. There were three
types of hand pumps, privately owned, government hand pumps and
other community owned hand pumps. The privately owned hand pumps
were in the control of few individuals while most others did not
under construction plinth for hand pump installation of the hand
pump new hand pump during the floods problem of water contamination
hand pump submerged during floods plan explaining the raised platform
design of hand pump have access to them. The government owned
hand pumps needed permissions from the water-supply department.
The department informed that once the repair-modification was
done to the hand pumps, it would become the liability of the organisation
to ensure its functioning and the government would not be responsible
for its working. It was also observed that many of these hand
pumps were very old and may get damaged during the level raising.
Discussions with other organisations that had modified the hand
pumps in the past showed that this option was not viable. It was
then thought that the community owned hand pumps could be taken
up for level raising. However on further analysis, it was observed
that they were of very inferior quality, since the local administrative
body or community themselves had installed them with very limited
monetary resources available to them. Hence the water quality
from the pump even in normal times was questionable.
Community
consultations led to the decision that the new hand pumps would
be installed on a raised plinth that was above the highest flood
levels observed in the past. After exploring different options,
locally available hand pump was selected. In addition to being
a ‘power-pump’ that fetched more water with less effort,
the selected pump had a few technical advantages (besides the
raised level) over the existing pumps. The pump used double filtering
with perforated extra casing pipe which was filled with gravel,
in addition to the nylon filter wrapped around the pipe. The PVC
used for the pipe was of higher quality than that was normally
used for hand pumps in the region. It also had better detailing
due to the double pipes at the joint near the pump handle. Hence,
the contaminated water did not seep into the pipe from the top.
The pump used, locally available components, hence its details
of joinery could be understood and repaired locally. Additionally
the pump was manufactured in a nearby town of Barabanki, making
it easier to approach the manufacturer directly in case of repair
or replacement.
Several
platform designs for accessing the raised pump were considered.
Two main designs were further worked out involving local masons.
One used the similar technique of plinth raising used for the
shelter. This was economical, easy to make and repair. The second
design with provision of steps from all the four sides was developed
with the help of a designer. After examining both the options,
the community came up with third option, which was a combination
of the above two mentioned designs. It used a bricks base with
cement plastered plinth and used the area of the platform more
efficiently. Hence the cost was controlled. The construction of
the platform was also executed under the cash-for-work activity
of the project. The table below shows the number of hand pumps
installed along with the main user group of the pump in each project
village.
 
 
Supporting Emergency
Livelihood Needs through Cash-for-Work
The cash-for-work approach in the project was seen as an integral
part of the project for accomplishing the construction work. This
activity focused on the livelihood issue and also helped, strengthen
the community’s skills in the areas of masonry construction
and bamboo crafts.
Most
of the people in this region are marginal farmers or landless
labourers. With very little land they barely manage to produce
enough for themselves. Wage labour is the only opportunity to
supplement their income. During and after the floods, the biggest
problem is that there is no labour work available for days together.
As the crops are destroyed and due to the non availability of
daily labour work, the families face severe hardship. It was important
to create a livelihood option that could be a source of income.
The construction work for the project provided such an opportunity
for the locals.
Under
this Scheme, total 6010 labour days were required for the entire
project. This was divided amongst five villages of project area
as per prevailing wages under similar government under cash-for-work
component. Total Rs. 6,34,915 were disbursed under this component
amongst villagers as the labour employment. digging and filling
of earth at housing plots as well as hand pump raising sites,
preparation of under-roof and bamboo mats for screen walls, and
hand plastering of floors and walls with mud and construction
of hand pump platforms.
Process:
The
wage computation of cash for work programme was made after studying
the schedule of rates under National Rural Employment Gurantee
Act (NREGA). People’s point of view was considered to fix
the daily wage. Finally the wage rate was fixed at Rs.100/- for
one person per family. It is a daily wage and not against piece
rate. People take responsibility that full work is done by all.
Several
meetings were held with the village panchayats for implementing
cash-for-work scheme. It was decided that this activity would
provide work opportunities to as many people as possible in the
villages regardless of them being selected for shelter construction.
Surveys were carried out in the villages for listing out the families
that would need financial support. It was important to find out
that if they were selected, would they really be interested in
working, as some of them might not prefer to do construction labour.
It
was estimated that approximately 6000 man days of work was required
for the shelter construction and raising the levels of the hand
pumps. It was estimated that the work would be distributed equally;
hence 1200 days or 60 people/ families would be given opportunity
to work for the project.
In
one of the village meetings the employment opportunity available
within the project was announced. To be part of the cash-for-work
activity, the selected people were required to fill an application
form and agree to the rules of the scheme decided by the project
team along with village panchayats.
The
rules are as described below -
-
Employment
would be provided to one person from the family. Women would
be given priority for employment.
-
A
card would be issued to the selected person. The card would
give them the opportunity of 20 days of work at the existing
NREGA rate of Rs 100.00 / day.
-
Payments
would be done on a weekly basis, usually on monday.
-
The
person working for the scheme would be insured for life.
-
First
aid kit would always be available on the site.
-
Drinking
water and shed would also be available on the site.
While
selecting the people for cash-for-work, priority was given to
the poorest of poor families. Whenever possible, the woman of
the family was selected. Job cards were made for the selected
people which guaranteed twenty days of work.
As
shown earlier, 6010 labour days were utilised at the end of the
project.
 
 
Disaster Preparedness
Disaster preparedness requires community capacity to build resilience
to risks so that the impact is reduced and people recover and
build back as quickly as possible. This is linked to reducing
structural vulnerability in terms of housing, water etc. and building
capacity for early warning and efficient evacuation at the time
of disaster. It not only develops local systems to deal with disasters
but also builds community confidence for resilience.
Present
situation and needs:
As initial analysis and community consultations suggested that
neither the government nor the people were prepared for the annually
recurring floods. It was therefore a must to develop flood resilience
amongst the people, village panchayats and the block administration
in line with the vulnerability and risk assessment done with the
people.
The
region did not have any early warning systems. From their experience
and informal news the people would prepare themselves for the
floods. Usually they would rush and climb on the bund situated
towards the west side of these villages (see the map of region).
They would spend a few days on the bund till the water level receded.
Though there would be very few casualties, there was heavy loss
of assets, especially domestic animals. Sometimes the village
panchayats had access to boats but there were no trained persons
to operate the oars. The boats were usually operated with long
bamboo. This method was not efficient. Controlling the boat in
whirlpools and navigating in the right direction was an issue.
Some people managed to swim and reach safer places but rescuing
others or carrying cattle and household articles to safer places
was very difficult.
Also,
snake and scorpion bites, and injuries during the floods were
some of the other issues that the villagers had to deal with without
having proper medical facilities or knowledge of first aid. Keeping
all these in mind, a comprehensive disaster preparedness program
was devised along with the community.
The
disaster preparedness activity had three main components.
-
Strengthen
community response mechanisms/capacity for early warning and
evacuation
-
Equip
the community volunteers with rescue materials and equipments
-
Train
people to use those equipments for better preparedness
Developing
systems and government mechanisms:
The
village panchayats would be the first to respond in a flood situation
but they lacked any equipments or orientation. The main issue
was the lack of a warning system and coordination with block level
administration to establish communication for warning against
flood. After discussing the issue with the village panchayats
and the block administration, an early warning system was established
through telephone line. Thus, the villages would be informed of
the possible floods much in advance. This would give them time
to safely reach the bund and also save their assets.
Providing
equipments and materials for flood resilience:
The
main need of the village panchayats was to have access to boats
and life saving equipments like life-jackets and life-buoys. The
panchayats did not have resources to acquire the boats and equipments.
On analysing the past floods, it was realised that the water level
was generally low, and that wooden boats with oars would be best
suitable for rescue operations as it can operate in up to 2 or
3 feet deep water, and could be controlled efficiently with basic
trainings. Also, it was cheaper to acquire as well as operate
them as it did not require any fuel. Maintenance would not require
sophisticated technical knowledge and could be done by the carpenters
after providing them some basic training. Each panchayat was supplied
with six wooden boats with oars. Each boat had three life jackets
and two life buoys. ten sets of life buoys and life jackets were
kept separately for emergency distribution. Since the smaller
unit of a village was a purva, it was discussed with the village
panchayats that the boats would be distributed in different purvas,
thus making it always available to the people in the hour of the
need.
In
addition to the wooden boats, one motorized boat was provided
to each village. At the same time, block level administration
did not have any motorized boats. It was also realized that Kohali
village (selected for the project) was a small village having
just two purvas and was situated very close to Kandauli village
as well as the bund. Hence it was decided that it can share the
boats with Kandauli village. Similarly, Matarepur village is located
very close to Baghahiya village, hence both these villages could
share one motorised boat. It was also observed that although Godahiya
No 4 village was not included in the project for shelter construction
and hand pumps level raising, it was quite prone to flooding and
suffered a lot of damage during the last floods. Thus it needed
mechanized boats as well. The motorized boats were therefore distributed
to Kandauli, Chulambha, Baghahiya and Godahiya No. 4. villages.
As there was no flood resistance mechanism at the block level
it was also thought necessary to provide one motorized boat to
the block administration. The motorized boat would help them reach
out to other villages and more people could be saved. The table
below shows the boat distribution amongst the different panchayats
and block administration.
| S.No. |
Allotted
to |
Motorized Boat (No.) |
Wooden
Boat (No.) |
| 1 |
Baghahiya Panchayat |
1 |
6 |
| 2 |
Kandauli Panchayat |
1 |
6 |
| 3 |
Godahiya No.4 Panchayat |
1 |
- |
| 4 |
Chulambha Panchayat |
1 |
6 |
| 5 |
Kohali Panchayat |
Shared with Kandauli |
6 |
| 6 |
Matarepur Panchayat |
Shared with Baghahiya |
6 |
| 7 |
Kaisarganj Block Admin |
1 |
- |
|
Total |
5 |
30 |
 

 
Trainings
for flood rescue and first aid:
It
was important to train the people for flood resilience so that
they could save not only their own life but also help save other’s
lives, as well as assets, cattle etc. Efforts were therefore made
to identify the local techniques and equipments for flood resilience.
Through games (with children) and street plays, lot of information
regarding the flood situations and how the villagers dealt with
it was gathered. Local volunteers suggested that in some situations
the local knowledge would work but a formal training would be
required to strengthen their skills. Training was required in
better swimming techniques, using life jackets and life buoys,
and first aid. To have better control over the wooden boats during
the floods, peoples’ skills for rowing these boats had to
be upgraded. It was also realised that since the motorised boats
were new to them, they would require special training on the same.
A
training institution by the name ‘Monters, Nuka Talim Kendra’
from Vadodara was identified and contacted for the training in
flood resilience. A three day training programme, in coordination
with them was organised in December 2008. Few young and enthusiastic
individuals who were going to remain in the villages were identified
from each village. The training programme included different aspects
of flood resilience such as operating the boats, swimming and
rescuing. First aid training was also provided by a Red Cross
trained instructor.
In
the boat training, different skills for rowing the boat, turning
the boat, stopping the boat immediately and rowing in a whirlpool
were covered. The training also included how to use the life jacket
and how to save oneself and others with the life buoy. The villagers
were also trained to swim efficiently by avoiding obstacles that
were common in flood situations. The training also covered rescue
operations for others, including people, cattle, and other assets.
The first aid training included saving life of the flood affected
person, carrying the injured and disabled in water, through boat
or on road, and simple techniques of making stretchers. Special
first aid training was also given for snake and scorpion bites
that are very common during the floods. The training concluded
with a mock drill / real life situation at the water stream near
the bund where all the participants enthusiastically took part
along with other villagers. They demonstrated their skills in
boat rowing, saving life and livestock, as well as assets, first
aid, etc. In February 2009, another training was organised with
help of motor boat manufacturing company ‘Sensea Marine
Services’, Kolkata, for the driving and maintenance of motorised
boats,. The training included theoretical explanations on the
working of the boats, practical training for driving and maintaining
the boat, using life jackets, life buoys, ropes, anchor etc. The
on site training also included checking the boats, understanding
different aspects of the boat’s functioning and installing
the engine. This training was attended by selected trainees from
the village panchayats and block administration. Since the boats
would remain with the panchayats, the head of the panchayat, known
as the ‘Pradhan’ also participated in the training.


Training
in Flood Resilience
-
using
life jackets
-
rowing
boats and rescue operations during floods
-
using
life buoys to save the drowning person
-
first
aid training and saving the lives

Motor
Boat Training
-
theory
of andinformation on motorised boats
-
driving
lessons on river Ghaghara for trainees


Rescue
operations during the project tenure: putting the training to
real life situations in floods of monsoon, 2008
-
bringing
people to the bund from villages
-
saving
live-stocks with help of life jackets- using techniques explained
during the training for flood resilience
-
helping
old aged people to reach to safety
Learnings
and Challenges:
This project aimed to demonstrate community based disaster risk
reduction practices. The project was able to establish that with
community level awareness building, training and various local
material support could develop their disaster preparedness. While
the project has targeted the vulnerable families to develop a
sense of shelter security by raising the homestead plots and hand
pumps, it has covered the entire community of five panchayats
for preparedness to respond to flood risks.
-
People’s
Knowledge and Practices Provide Best Options
The houses of the poor people used to get damaged recurrently
by annual floods of river Ghaghra. They do not afford to invest
in housing year after year. It was learnt from the community
that if the homestead plots are raised above the flood risk
level the houses will not be damaged. It will develop a sense
of permanency and people will slowly and incrementally invest
on housing. It need to be emphasized that Bamboo as a walling
material in the form of wattle and daub which used to be n
practiced earlier has been gradually out of practice as people
stopped investing in houses. The project could revitalize
the traditional walling technology by closely working with
the people.
In the flooding
years there is a paucity of thatch for roofing as the rice fields
are damaged due to denudation of the agriculture fields. Local
people prefer corrugated tin sheets as the roofing material. The
project introduced Micro Concrete Roofing (MRC) tile prepared
by a mason guild promoted by Development Alternatives, an NGO
in nearby cities. This roofing material was introduced as there
is immense scope to introduce production of MCR tiles locally,
thereby creating an alternate source of livelihood. Although this
idea was demonstrated, it did not materialize into any production
unit in the region. This can be taken up as a future initiative
not only for safe housing but also for alternate livelihood option.
The scope of
the project is dependent upon the extent of people participation.
When the homestead plots were raised, people could feel their
internal resilience to flood risks. This has increased their sense
of ownership and participation in the entire process of the project.
The project has brought out multiple options on use of technology
and materials from people’s own experience. It was empowering
for all the people that they were making their own choices rather
than some external ‘expert’ making those choices for
them. To cite another example, it was a commonly suggested solutions
to raise the level of entire settlement to address the flood risks.
However, the villagers felt that it will require large mass of
earth to be excavated from outside which will be costly and may
not be feasible looking into the geographical terrain. People
opted for raising the homestead plot only. Even such small amount
of earth was difficult to acquire at times. In the hindsight,
such a people’s decision to raise homestead plot instead
of the entire settlement helped in maintaining the natural scope
without disturbing the flood current. An artificial obstruction
may have potential to create many adverse effects which the people’s
wisdom and practices have averted.
It was not
possible to acquire a large plot from where the earth could be
dug up for a sizeable number of homestead plots. Small area of
individual agriculture plot was identified for soil excavation.
People find it beneficial as agriculre field would be filled up
again with silt during the next monsoon floods adding to the fertility
of the land. Hence there was no long term negative impact of the
activity on the land and environment.
-
Simple
Activities Have Better Chance of Mainstreaming
Incorporating the cash-for-work activity in the project helped
demonstrate how the local governing body, Panchayat could
utilize various government schemes like NREGA for building
useful assets for the village that would help build disaster
resilience, in addition to providing just employment to the
people.
Raising the
level of the hand pumps was another successful activity which
is now being undertaken by the government for the already existing
government installed hand pumps in the region. Before erecting
the high level hand pumps the water needs to be tested to examine
possible contamination. The project has tested the quality of
water of the hand pumps. The project has also made efforts to
train the local people on testing of water. Simple water kits
were procured with the help of a reputed government organisation
working in Gujarat (WASMO). The water testing by local people
could not be fully achieved due to short time frame of the project
which can be further taken up.
While designing
the project it was also consciously decided to keep the material
costs as low as possible such that more money could be put into
labour intensive activities, thus boosting the local economy.
It was made possible, as people defined the different factors
of the projectand found solutions themselves which increasedthelabour
component.
-
Need
For Further Exploration
Sanitation is another issue in housing that could not be addressed
in this project. What kind of system should be used in such
areas that are prone to heavyfloods needs to be explored.
While plastic tank as septic tank was considered as one of
the options, that does not contaminate the ground water but
it costs high and also requires frequent cleaning. The issue
of toilets in the region is very important and needs to be
taken up as a priority. It can be resolved only through constant
experimentation.
-
Community
Based DRR Need to Recognise Capacity Buidling of Both the
Community and Administration
As for the disaster preparedness, it was realized that the
materials or facilities provided should have a use in daily
activities as well. Local boats were a good example in this
case. Motorised boats were more expensive and require costly
maintenance while local wooden boats were cheaper and easy
to use. In terms of utility, wooden boats fared better and
could also be used for transportation of people and goods
regularly. The mechanized motor boats, could be best used
if put at the Block and district level in command of the government
disaster response. It can serve a larger population and increase
the capacity of the administration for efficient response.
The issue of increasing capacity of community and local administration
need to be viewed together for better response mechanisms.
-
Make
the Coordination Simple by capacitating Local Partners
This project required long distance coordination between UNNATI
in Gujarat and partner organisations in Uttar Pradesh. In
order to reduce such long distance coordination, perhaps there
is a need to develop SSK as a state resource center for disaster
risk reduction.
Overall,
it was a small scale intervention for the annually recurring
floods, which marks the beginning of developing community resilience
for floods in the region. Long term disaster response should
be planned for the region. SSK is planning to get involved with
disaster preparedness programmes along with the support of Malteser
International and Unnati.
|